7/2025 – Terraforce® L11 Blocks Transform Complex Road Infrastructure Project
Creating a Direct Route Through Challenging Terrain
Located on Perron Street in Vredenburg, an ambitious infrastructure project has successfully connected the main road to the Louwville Area through what was once a challenging valley terrain. The project, which required filling to a maximum height of 7.5 meters, demonstrates the versatility and aesthetic appeal of the Terraforce® retaining wall system.

Project Overview
The construction of this new roadway was initiated to create a direct route between Vredenburg’s main road and the Louwville Area, eliminating the need for longer alternative routes. The project involved substantial earthworks and sophisticated retaining wall construction through a valley section, requiring careful engineering and precise execution.


Why Terraforce L11 Round Face Blocks Were the Ideal Choice
The project team selected Terraforce® L11 blocks in round face finish for several compelling reasons. Says Dale Meyer, WCB Group: “The system’s inherent flexibility proved crucial in accommodating the varying parameters of the roadway, both vertically and horizontally. As the road undulated through the landscape, the Terraforce system adapted seamlessly to these complex geometric requirements.
“Aesthetics played an equally important role in the decision. The round face finish of the L11 blocks provided an attractive scalloped appearance that enhanced the visual appeal of this prominent infrastructure project, ensuring the retaining wall would be a positive addition to the community landscape.”
Engineering Excellence in Complex Terrain
Meyer adds that the installation process showcased the adaptability of the Terraforce system: “Beginning with carefully positioned cast footings, each individual section was methodically laid and stacked from start to finish, building up to the final height. The construction methodology included concrete filling of the lower and upper courses, while the entire height was reinforced with geotextile tie-backs for enhanced structural integrity.”



Overcoming Construction Challenges
The project presented unique challenges that required innovative solutions and meticulous planning, according to Meyer: “The setting out requirements were particularly elaborate, demanding extensive preparation and careful calculation. The roadway being retained undulated horizontally while simultaneously decreasing in height from start to finish, creating a complex three-dimensional puzzle.
“Adding to the complexity, there was a dramatic 15-meter height difference from the start point to the end point at road level, coupled with separate ground level variations that rose and fell throughout the site. These multiple elevation changes had to be precisely accommodated in both the design phase and the calculation of setting out positions for individual footings and the face line alignment of all initial blocks.”

Project Timeline and Scale
Construction commenced in March 2023, with the Terraforce section beginning in July 2023 and reaching completion in March 2024. This ambitious timeline was maintained despite the project’s complexity, demonstrating effective project management and construction expertise.
The scale of the project is impressive, requiring a total of 30,965 Terraforce®L11 blocks to complete the retaining wall system. This substantial quantity reflects both the length and height of the installation, making it a significant Terraforce® project in the Western Cape region.




Future Development
Saldanha Bay Municipality has committed to handling future landscaping initiatives, which will further enhance the aesthetic integration of the retaining wall with the surrounding environment.
The project not only solved a practical transportation need for the Vredenburg community but did so in a way that enhanced rather than detracted from the local landscape, proving that functional infrastructure can also be aesthetically pleasing.
Project Team
The project’s success resulted from collaboration between experienced professionals:
- Design: Terraforce wall design by Simon Knutton, KCE Consulting Engineers
- Engineering: Siroccon, with John Render providing geometric design of the road and contract administration
- Construction: WCB Group served as the main contractor, managing all aspects of the build
- Terraforce licensed block manufacturer: Van Dyk Precast