10/2019 – Standing Strong: Herolds Bay Sea Wall

Seashore protection with Terraforce

Herolds Bay is a small, quaint seaside village in the southern Cape Province. It is known for its sheltered location and idyllic beach, that occasionally comes under attack by the sea in winter. During these months, the homes built closely to the beach need protecting from the waves reaching all the way up their front doors, causing flooding and damage.

Aerial shot of the Terraforce wall, 2006
Aerial shot of the Terraforce wall, 2006
The Terraforce wall in October 2019!
The Terraforce wall in October 2019

The former retaining structures prior to the Terraforce retaining wall installation in 2004, were structurally ineffective and not aesthetically acceptable. The client, George Municipality, therefore instructed the construction of an improved beach protection wall that would satisfy both structural and aesthetic requirements.


Project team

Engineers: Tuiniqua Consulting Engineers, George Office 

Contractor: New Heights

Terraforce licensed block manufacturer: Mobicast


The upgraded and improved wall in 2019

The retaining wall protecting homes close to the beach
The retaining wall protecting homes close to the beach
Terraforce river inlet
Terraforce river inlet
Terraforce stair detail
Terraforce stair detail
Far end of installation abutting solid rock
Far end of installation abutting solid rock

Aesthetic but durable sea barrier

Says Paul Goedhart, Pr Eng, Tuiniqua Consulting Engineers, who conceptualised the new wall in 2004: “The old Herolds Bay beach protection wall, was up to that point a combination of various materials and construction techniques, was frequently damaged during winter storms and the Municipality wanted a new uniform wall between the beach and the road which would withstand the sea forces but would also provide an accessible and aesthetic barrier. To meet these requirements a stepped reinforced Terraforce wall was designed. The wall was founded on the underlying rock since the level of the beach sand varies due to the wave action. In so far this was possible the old wall structure was left in place.

“Where the depth of the rock level was unpractical for normal excavation the wall was built on a reinforced concrete strip footing which was founded as deep as practically possible. A reinforcement fabric was used to anchor the wall to the compacted cement stabilised backfill material behind the wall and enough drainage was provided to reduce hydrostatic pressures. The top of the wall was finished off with an in-situ concrete coping.”

Construction of the new wall was started in April 2004 and was completed in October of the same year. During that time the team was challenged by high sea levels and high-water table.

Work in progress on the wall in 2004
Work in progress on the wall in 2004
Shuttering for concrete barrier
Shuttering for concrete barrier

13 500 custom-made Terraforce blocks

Goedhart explains why the Terraforce retaining wall system was chosen: “Terraforce L13 blocks were chosen due to the substantial constructed mass that they offer, and 13,500 units were made with a custom-made concrete mixture – 30 MPa with a minimum of 400 kg cement per m³ of concrete – by Mobicast, Southern Cape Terraforce licensed manufacturer. The stepped wall creates an accessible interface between the beach and the roads/lawns. The blocks could also be easily secured together with reinforced concrete and the transition to ramps and stairs was easy to achieve.”

In 2008 the Municipality commissioned some upgrades and extensions to further strengthen the wall to ensure that it would weather all storms and it is now standing strong for 14 Years!

Caisson and foundation
Caisson and foundation
Installing gabion sacrificial layer
Installing gabion sacrificial layer
Underpinning due to the uneven rock formation
Underpinning due to the uneven rock formation
Casting concrete barrier
Casting concrete barrier

Withstanding the storms…

Withstanding storms till now!
Withstanding storms till now!
Terraforce sea wall, Herolds Bay
Terraforce sea wall, Herolds Bay

Project team


Engineers: Tuiniqua Consulting Engineers, George Office

Contractor: New Heights

Licensed Terraforce block manufacturer: Mobicast