10/2018 – Large scale erosion control on the West Coast with Terraforce
Slope rehabilitation with Terraforce, Pepper Bay Harbour
Initiated by the Department of Public Works as custodian of state land, this large retaining wall is located on the West Coast, Pepper Bay harbour area, to stabilize existing eroded embankments in the interest of public safety.
Project team
Client: Department of Public Works
Main Contractor: Guerrini Marine Construction
Consulting Engineer: Ulwazi Consulting Engineers
Terraforce Block Supplier: Van Dyk Stene, West Coast
2.5km of destabilised slopes
The embankments consist of multiple layers of sedimentation up to 21m in height and 2.5km in length, where softer material has eroded leaving harder layers of overhanging and unstable rock. The Terraforce retaining wall system was specified by the consulting Engineer, Ulwazi Consulting Engineers, as offering practical, stable, and weather resistant surface protection.
A trusted industry brand for 40 years
Terraforce is a member of the Concrete Manufacturers Association (CMA) in South Africa and adheres to the Canadian and US international Standard Specification for Load Bearing Concrete Masonry Units, following a successful ICBO (now ICC-ES, a leading US nonprofit, limited liability company that does technical evaluations of building products, components, methods, and materials) evaluation in 2002.
The Terraforce earth retaining system was also extensively tested by Hawkins Hawkins & Osborne Consulting Engineers, South Africa in 1992, resulting in a comprehensive design and specification manual and user guide. Composite retaining wall design and construction procedures with Terraforce blocks have been subjected to rigorous laboratory tests. These were conducted on a large-scale test apparatus to evaluate the mechanical performance of, among others, the connection between blocks and grids. In all tests the primary mode of failure was rupture of the geogrid outside the blocks and performance was found be above average based on experience with many systems tested over many years.
Terraforce products also undergo regular MPA testing, locally and overseas. Currently the blocks are undergoing further shear resistance and geogrid connection tests at Curtin University, Perth, Western Australia, guided by Johan Joubert of Wave International, results of which will be made available once tests are completed.
Stabilising a dangerous slope
Before block installation could begin, all vegetation and loose material had to be removed to expose the underlying rock face of the embankments. Says Adriano Guerrini, of Guerrini Marine Construction:
“These were swept clean and benched for slip prevention, so the extent of stabilising could then be determined and the angle (generally between 60 and 70 degrees to the horizontal) of the final face slope set out. Using soil-crete (sand: cement mix) the rock face was covered by backfilling in well-compacted layers, with depth of the backfilling being monitored and minimised to follow the natural contours of the exposed face.
“At the same time the block facings were built up and the blocks filled with soil-crete, stepping back towards the rock face where appropriate, to minimise depth of backfill and reduce the visual impact of a sheer wall. Finally, the tops of the step-backs and the finished level are capped with a concrete slab.”
Job creation and on-site training
Some of the challenges encountered and successfully managed during installation included the continual navigating and assessing of the steep, 15m high, heavily vegetated terrain with cranes and telescopic handlers. An estimated 180 000 blocks, supplied by Van Dyk Stene, Terraforce manufacturer on the West Coast – with 100m² backfill sand per 1200 blocks (100 m2) – were installed using 5 TLB loaders, a 20 000 litre water truck and 80 labourers, of which 90% are local untrained labour, who underwent onsite training.
Also, under the auspices of the Expanded Public Works Programme, 25 official learners were given basic construction skill training over a period of approximately three months. On completion in March 2018, indigenous plants were planted by a company specialising in establishing the sensitive vegetation of the West Coast.
References and test results for Terraforce blocks
- Guide to the design of Terraforce retaining walls, Oct. 1992 by W G Technau of Hawkins, Hawkins & Osborn. Rivonia, South Africa.
- Guidelines for the use of the Terraforce retaining wall design spreadsheet, Nov. 1994 by G Bentel of Steffen, Robertson & Kirsten. Technology Park, W Australia.
- Terraforce, the living retaining wall system: Design and installation manual for geosynthetic reinforced soil applications, Feb. 1996 by Dr Richard J Bathurst of Royal Military College, Kingston, Ontario and Colin Alston of Alston Associates Inc., Markham, Ontario, Canada.
- Terraforce design manual for Boral Besser Masonry Ltd, Oct. 1997 by Andrew Shirley of Shirley Consulting Eng. Sydney, Australia.
- Crushing tests of blocks subject to line loading, July 1998 by Damon Clark Associates. Durban, South Africa.
- Connection tests and interface shear tests, Nov. 1998 and Feb. 1999 by Dr Richard J Bathurst of Royal Military College. Kingston, Canada.