Brief installation guidelinesPlanning
Please note: When building composite walls of any significant height, it is of crucial importance to consult with an experienced engineer. The law is very strict on these matters, with The NHBRC requirement stating that one can build a wall to a height of 1.2m without consulting an engineer, but as a general rule 1.5m for walls no steeper than 70º is also possible. Any steeper and especially load carrying walls must be designed by a qualified engineer, even if only 1.2m high.
Design and Construction DetailsBelow are three basic visual guides describing the installation process, PDF format:
See below to view a step by step photographic illustration on how to install Terraforce retaining blocks. Remember to always ensure a good/correct foundation and drainage system are installed. This will prevent any unwanted ground movement that could cause damage to your retaining wall.
1. Prepare a level foundation, gravel or concrete as directed by site conditions. Compacted gravel foundations are usually sufficient for structures not higher than one (1) meter. On sloping sites the foundation may be stepped by block height at intervals to suit the slope.
3. Install drainage pipe with outlet and free draining backfill as specified behind first row of blocks. A length of flexible pipe will assist in setting out smooth curves.
5. Continue construction, row by row while backfilling and compacting free draining material as each row is completed with topsoil infill. In situ or precast interlocking keys to be installed when directed by the engineer.
7. Terraced walls must be well founded. Individual foundations as specified or as shown, on a double row of blocks on well compacted backfill.
|
|||||||||||||||||||||||||